Jermuk Post

Renovation of Jermuk Post
Metal Sheet for the roof   51 x 4250AMD= 216,750 AMD
Gypsum for the wall          7 x 7600AMD= 53,200 AMD
Profile for gypsum             12m x 1000AMD= 12,000 AMD
Metal Screw 1 box              1 x box=4800 AMD
Profile Screw 1 box            1 x box=5500 AMD
Double Profile 1 box          1 x box=1200 AMD
Shutex Paint 10L                1 x 10L=9300 AMD
Electric wire                        50 m x 145 AMD=7250 AMD
Transportation                   70,000 AMD
Total                                     388,000 AMD
Cement                                4.5 ton x 54,000=243,000 AMD
Bloks                                    500 x 160 AMD=80,000 AMD
Total                                    323,000 AMD
Grand Total                        711,000 AMD
Estimated Project Cost
$1,900.00
Funds requested from ADF
$1900.00
Project Executor
Project Start Date
April 3, 2023
Project End Date
April 9, 2023